When is the right time to order windows during construction?

Find out at which stage of construction it is best to order windows, how long they take to make and what has to be decided before ordering to avoid delays.

The best time to order windows is when the foundations are finished and the walls are going up: by then the dimensions of the window openings are clear, yet there is still enough time for production. Ordering too early can cause storage problems, while ordering too late delays the whole build.

How long you have to wait

Our production time is usually 4–8 weeks, depending on the complexity of the project and the factory workload. In spring and summer, the building season, demand is usually higher, so it is advisable to order a little earlier at that time.

What to decide before ordering

  • Profile colour and finish
  • Type of glazing unit — double or triple
  • Opening type for each window
  • Handle style and extras such as window sills and insect screens

Changes after production has started can be expensive or even impossible, so these decisions are best made during the site measurement together with a specialist.

Prepared by Logu Pasaule — a window and door manufacturer with a factory in Stalbe, Cēsis Municipality.